I have to complete the below project, the timeline is 24hrs. if you know you can do it apply to it.
You have signed a contract to build a garage for the Simpsons. You will receive a $500 bonus for completing the project within 17 working days. The contract also contains a penalty clause in which you will lose $100 for each day the project takes longer than 17 working days.
Draw a project network given the information below. Complete the forward and backward pass, compute the activity slack, and identify the critical path. Do you expect to receive a bonus or a penalty on this project?